Activity differents work times for the same item
Dear all
I have a process with 1 item and 3 phases. Phase 1 use Activity 1 for 4 minute, Phase 2 use Activity 2 for 5 minutes and phase 3 -> Activity 1 for 10 minutes.
How can I parameterize Activity 1 with different work times for the same item??
Thanks in advance.
Best regards!
Comments
Was this answer helpful?
0
Hi
i often use Multi-tasking in such a case: https://www.simul8.com/support/help/doku.php?id=features:multi_task_timing ,but if you are using the Basic version this might not be available.
In that case, could you try creating 3 Separate Activities, assign them to a Group and limit work items to 1? That way only 1 item will be processed among these 3 Activities at a time. Here's something that explains Groups: https://www.simul8.com/support/help/doku.php?id=features:groups
Guilia
BetweenComments (1)
Was this answer helpful?
0
Thank you very much for your respond.
BetweenComments (2)
Was this answer helpful?
0
Thank you very much for your respond.