i have a question

boZongboZong
Created at
in Community support

i have two process,then both of priority are same(EX:50),and they need the a same resource(EX:doctor),
my question is :At the same time, both processes need resources, how to choose the resources of simul8



Comments

  • Was this answer helpful?


    0

    As Simul8 is a Discrete Event Simulation, when two work items are due to arrive into an activity at the same time, one event will happen before the other and the resource will go to the one that is scheduled to happen first, even though this will all happen at exactly the same clock time.

    Hopefully this answers your question!